151 East 58 Street
Analysis
The building’s over‑built status and lack of an arm‑length sale drive a medium risk rating despite clean violation and penalty records.
The good
- no enforcement or safety violation penalties owed
- no open violations per residential unit
- no legal proceedings and not on a tax lien list
- substantial number of permits indicating active maintenance
The bad
- built beyond the residential floor-area limit (13.08 FAR vs 10 limit)
- no arms‑length sale recorded, market value on record is zero
- average unit size of 10,506 sq ft suggests unusually large units and limited rent‑per‑sq ft potential
Written by a language model from this property's own figures — the same numbers shown on this page. It introduces no facts of its own: every figure it cites is checked against the data before the text is shown. It is a reading of the numbers, not a professional opinion, and it can be wrong about emphasis even when it is right about arithmetic. See our methodology.
What the numbers say
Generated from this property's own figures using the rules set out in our methodology. Every statement below refers to a number shown on this page.
Already larger than residential zoning would allow
The building occupies a floor-area ratio of 13.08, against a residential limit of 10.00 — it is over that limit by 3.08. A building in this position almost always predates the current rules and is legally non-conforming: it may generally remain, but it typically cannot be enlarged for residential use, and it may not be rebuildable as it stands.
A light open-violation load
Only 1 violation is currently open across 105 residential units, with $0.00 outstanding. For a building of this age that is a modest figure.
Development & zoning
Floor-area ratio
| Built | 13.08 |
|---|---|
| Residential limit | 10.00 |
| Commercial limit | 10.00 |
| Community-facility limit | 10.00 |
Development headroom (calculated) calculated
| Highest permitted ratio | 10.00 |
|---|---|
| Unused ratio | -3.08 |
| Unused buildable area | — |
| Lot area | 84,348 sq ft |
Value & taxes
Assessment
| Assessed total | $550,589,853 |
|---|---|
| Assessed land | $72,000,000 |
| Assessed building | $478,589,853 |
| Market value on record | $0 |
| Assessed as % of market | — |
Tax
| Tax class | 2 |
|---|---|
| Taxable assessed | $0 |
| Tax rate | 12.502% |
| Estimated annual levy | — |
The levy is an estimate — taxable value × the published rate for the class. It does not account for exemptions or abatements the property may carry, and will not match an actual bill. It is not the property's total debt to the city: unpaid tax and water arrears are not shown anywhere on this page.
Assessed value by year
| Year | Assessed value | Change |
|---|---|---|
| 2027 | $0 | — |
| 2026 | $0 | — |
| 2025 | $0 | — |
| 2024 | $0 | — |
| 2023 | $0 | — |
Building & occupancy
Structure
| Year built | 2001 |
|---|---|
| Floors | 54 |
| Building area | 1,103,169 sq ft |
| Residential area | 246,927 sq ft |
| Commercial area | 856,242 sq ft |
Occupancy
| Ownership | Condominium |
|---|---|
| Total units | 109 |
| Residential units | 105 |
| Residential Avg unit size | 2,352 sq ft (calculated) |
| Commercial Avg unit size | 214,061 sq ft (calculated) |
| Building class | RM |
Neighborhood, risk & energy
Neighborhood & transit
| Nearest subway | 59 St (4, 5, 6) — 0.07 mi |
|---|---|
| School district | 2 |
| Police precinct | 17 |
| Nearest firehouse | Battalion 8/Engine 8/Ladder 2 — 165 East 51 Street |
Location risk
| Flood zone | Minimal hazard (Zone X) |
|---|---|
| Hurricane evacuation zone | Not in an evacuation zone |
Energy & emissions
| Energy grade | C |
|---|---|
| Energy use intensity | 117.9 kBtu/ft² |
| Greenhouse-gas emissions | 17,022 metric tons/yr |
Comparable sales
| Address | Sale date | Price | Sq ft | $/sq ft |
|---|---|---|---|---|
| 485 Park Avenue, 1b | 2026-05-14 | $2,500,000 | — | — |
| 485 Park Avenue, 12fl | 2025-12-29 | $10,964,539 | — | — |
| 151 East 58th Street, 38c | 2025-12-23 | $12,000,000 | — | — |
| 151 East 58th Street, 38b | 2025-12-23 | $12,000,000 | — | — |
| 485 Park Avenue, 11 Fl | 2025-12-18 | $5,300,000 | — | — |
| 151 East 58 Street, 42c | 2025-12-11 | $3,200,000 | — | — |
| 151 East 58th Street, 45c | 2025-09-17 | $5,750,000 | — | — |
| 151 East 58 Street, Ph55w | 2025-08-21 | $16,500,000 | — | — |
Record activity
Compliance calculated
| Open violations | 1 |
|---|---|
| Open per residential unit | 0.0 (calculated) |
| Enforcement penalties | $0.00 |
| Safety-violation penalties | Not available |
| Total penalties owed | $0.00 (calculated) |
| On tax-lien sale list | No |
Activity
| Complaints recorded | 187 |
|---|---|
| Permits / alterations | 260 |
| Recorded documents | 0 |
| Legal proceedings | 0 |
Total penalties owed combines two separate debts — enforcement penalties (from summonses) and safety-violation penalties (unfiled inspections and reports on boilers, elevators, facades and energy use). The second kind accrues quietly and is routinely missed; it is a standing debt on the building, not a fine someone can walk away from. The safety figure could not be retrieved for this property, so no total is shown — we would rather show nothing than a total that silently omits it. Neither figure includes unpaid property tax or water and sewer arrears, which are frequently the largest number of all and appear nowhere on this page. For a true payoff figure, go to the city directly.
Ownership & last recorded sale
Owner of record
| Owner | One Beacon Court Condominium |
|---|---|
| Parcel | 1013137501 |
| Block | 1313 |
| Lot | 7501 |
Last recorded transfer
| Date | — |
|---|---|
| Recorded price | — |
| Price per unit | Not meaningful |
| Price vs assessed | Not meaningful |
Owner of record comes from the public land-use record and may lag a recent sale. It is frequently a holding company rather than an individual. If you own or manage this property and believe something here is wrong, tell us — we read and respond to every message of that kind.
Open violations
Open violations only. A violation that was raised and later corrected is not counted — an older building accumulates hundreds of those, and the number says more about its age than its condition.
| Issued | Category | Class | Status | Amount due | Description |
|---|---|---|---|---|---|
| 12 Jul 2011 | Building | — | V-Building VIOLATION - ACTIVE | — | C-CONSTRUCTION OTHER OPTIONAL |
Complaints
A complaint is an allegation, not a finding — many are dismissed. A sustained pattern is nevertheless informative about how a building is run.
| Date | Problem | Type | Status | Closed |
|---|---|---|---|---|
| 20 Jul 2026 | Non-Chronic | Homeless Person Assistance | Closed | 20 Jul 2026 |
| 15 Jun 2026 | Noise: Construction Before/After Hours (NM1 | Noise | Closed | 30 Jun 2026 |
| 2 Jun 2026 | Food Vendor | Vendor Enforcement | Closed | 2 Jun 2026 |
| 2 Jun 2026 | Air: Odor/Fumes, Restaurant (AD2 | Air Quality | Closed | 5 Jun 2026 |
| 31 May 2026 | Non-Food Vendor | Vendor Enforcement | Closed | 31 May 2026 |
| 28 May 2026 | Car Service Company Report | For Hire Vehicle Report | In Progress | — |
| 27 May 2026 | Leak (Use Comments) (WA2 | Water System | Closed | 27 May 2026 |
| 14 May 2026 | Car/Truck Horn | Noise - Vehicle | Closed | 14 May 2026 |
| 14 May 2026 | Car/Truck Horn | Noise - Vehicle | Closed | 14 May 2026 |
| 9 May 2026 | Loud Talking | Noise - Street/Sidewalk | Closed | 9 May 2026 |
| 7 May 2026 | Rough, Pitted or Cracked Roads | Street Condition | Closed | 7 May 2026 |
| 5 May 2026 | Driver Complaint - Non Passenger | For Hire Vehicle Complaint | In Progress | — |
| 5 May 2026 | Driver Complaint - Non Passenger | For Hire Vehicle Complaint | In Progress | — |
| 29 Apr 2026 | Posted Parking Sign Violation | Illegal Parking | Closed | 29 Apr 2026 |
| 29 Apr 2026 | Non-Chronic | Homeless Person Assistance | Closed | 30 Apr 2026 |
| 27 Apr 2026 | Driver Complaint - Non Passenger | For Hire Vehicle Complaint | In Progress | — |
| 9 Apr 2026 | Non-Chronic | Homeless Person Assistance | Closed | 9 Apr 2026 |
| 9 Apr 2026 | Non-Chronic | Homeless Person Assistance | Closed | 9 Apr 2026 |
| 4 Apr 2026 | Driver Complaint - Passenger | Taxi Complaint | In Progress | — |
| 29 Mar 2026 | Loud Music/Party | Noise - Residential | Closed | 29 Mar 2026 |
| 25 Mar 2026 | Loud Music/Party | Noise - Street/Sidewalk | Closed | 25 Mar 2026 |
| 11 Mar 2026 | Driver Complaint - Non Passenger | Taxi Complaint | In Progress | — |
| 3 Mar 2026 | Driver Complaint - Passenger | Taxi Complaint | In Progress | — |
| 6 Feb 2026 | N/A | Panhandling | Closed | 6 Feb 2026 |
| 2 Feb 2026 | APARTMENT ONLY | HEAT/HOT WATER | Closed | 7 Feb 2026 |
| 3 Dec 2025 | License Plate Obscured | Illegal Parking | Closed | 3 Dec 2025 |
| 4 Nov 2025 | Non-Chronic | Homeless Person Assistance | Closed | 4 Nov 2025 |
| 1 Nov 2025 | Driver Complaint - Passenger | Taxi Complaint | In Progress | — |
| 30 Oct 2025 | Driver Complaint - Non Passenger | For Hire Vehicle Complaint | Closed | 4 Dec 2025 |
| 9 Oct 2025 | Sewer Odor (SA2 | Sewer | Closed | 9 Oct 2025 |
| 2 Oct 2025 | Non-Chronic | Homeless Person Assistance | Closed | 2 Oct 2025 |
| 15 Sep 2025 | Non-Chronic | Homeless Person Assistance | Closed | 15 Sep 2025 |
| 28 Aug 2025 | N/A | Encampment | Closed | 28 Aug 2025 |
| 24 Aug 2025 | Driver Complaint - Passenger | Taxi Complaint | Closed | 3 Dec 2025 |
| 24 Aug 2025 | Rodents/Insects/Garbage | Food Establishment | Closed | 23 Oct 2025 |
| 14 Aug 2025 | N/A | Panhandling | Closed | 14 Aug 2025 |
| 14 Aug 2025 | N/A | Panhandling | Closed | 14 Aug 2025 |
| 14 Aug 2025 | Chronic | Homeless Person Assistance | Closed | 14 Aug 2025 |
| 14 Aug 2025 | N/A | Panhandling | Closed | 14 Aug 2025 |
| 2 Aug 2025 | Blocked Bike Lane | Illegal Parking | Closed | 2 Aug 2025 |
| 29 Jul 2025 | N/A | Panhandling | Closed | 29 Jul 2025 |
| 18 Jul 2025 | Parking Permit Improper Use | Illegal Parking | Closed | 18 Jul 2025 |
| 18 Jul 2025 | Neglected | Animal-Abuse | Closed | 18 Jul 2025 |
| 16 Jul 2025 | Noise: Alarms (NR3 | Noise | Closed | 18 Jul 2025 |
| 11 Jul 2025 | Parking Permit Improper Use | Illegal Parking | Closed | 11 Jul 2025 |
| 10 Jul 2025 | Loud Talking | Noise - Street/Sidewalk | Closed | 10 Jul 2025 |
| 7 Jul 2025 | Driver Complaint - Passenger | Taxi Complaint | Closed | 29 Sep 2025 |
| 28 Jun 2025 | N/A | Panhandling | Closed | 28 Jun 2025 |
| 16 Jun 2025 | Plate Condition - Noisy | Street Condition | Closed | 20 Jun 2025 |
| 5 Jun 2025 | N/A | Encampment | Closed | 5 Jun 2025 |
Showing the 50 most recent of 150. The full set is available in the interactive report.
Permits & alterations
The absence of a permit does not prove no work was done — it may equally mean work was done without one.
| Issued | Type | Status | Work |
|---|---|---|---|
| 25 Jun 2025 | Plumbing | Signed-off | APARTMENT RENOVATION (PH51W- 52M/50CO & 51M/49CO) WORK TO INCLUDE PLUMBING MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| 10 Jun 2025 | General Construction | Signed-off | Renovation of existing meeting room and open office space on the 7th floor. No change in use, egress or occupancy |
| 25 Feb 2025 | Plumbing | Signed-off | Plumbing work associated with the addition of restrooms on 28th and 29th Floors (27th and 28th Floors per CO) and showers on Lower Level 2 (Sub-Cellar #1 per CO). No change in use, egress or occupancy |
| 13 Feb 2025 | Sprinklers | Signed-off | Sprinkler work associated with the addition of restrooms on 28th and 29th Floors (27th and 28th Floors per CO) and showers on Lower Level 2 (Sub-Cellar #1 per CO). No change in use, egress or occupancy |
| 12 Feb 2025 | General Construction | Signed-off | Addition of restrooms on 28th and 29th Floors (27th and 28th Floors per CO). Addition of showers on Lower Level 2 (Sub-Cellar #1 per CO). No change in use, egress or occupancy |
| 20 Nov 2024 | General Construction | Permit Issued | APARTMENT RENOVATION (PH51W- 52M/50CO & 51M/49CO) WORK TO INCLUDE PARTITION, CEILING, AND DOOR MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| 19 Nov 2024 | General Construction | Permit Issued | GENERAL CONSTRUCTION FOR LIMITED INTERIOR RENOVATIONS OF APARTMENT 40F AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| 31 Jul 2024 | General Construction | Signed-off | Minor construction work to install pylons for ADA access buttons to open main entrance doors as indicated on drawings |
| 16 Jul 2024 | General Construction | Signed-off | Installation of security gates inside stairwells along the 2nd floor as indicated on drawings |
| 3 Jul 2024 | Plumbing | Signed-off | PL work as per plans filed. no change in use egress or occupancy |
| 1 Jul 2024 | Sprinklers | Signed-off | APARTMENT RENOVATION (PH51W- 52M/50CO & 51M/49CO) WORK TO INCLUDE SPRINKLER MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| 20 May 2024 | General Construction | Signed-off | minor interior work in apt 49D as per plans filed. no change in use egress or occupancy |
| 2 May 2024 | General Construction | Signed-off | minor partition demo work and associated finishes in apt 49D as per plans filed. no change in use egress or occupancy |
| 9 Apr 2024 | Plumbing | Signed-off | INSTALL NEW GAS PIPING TO NEW BUILT IN STOVE TOP AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS |
| 1 Feb 2024 | Mechanical Systems | Permit Issued | APARTMENT RENOVATION (PH51W- 52M/50CO & 51M/49CO) WORK TO MECHANICAL MODIFICATIONS AS INDICATED ON PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| 17 Jan 2024 | Boiler Equipment | Permit Issued | Modifications to existing fuel oil piping Eliminating one single fuel oil pump skid of 3 pumps and replacing it with 2 fuel oil pump skids each with 2 pumps |
| 1 Nov 2023 | Sign | Signed-off | ERECT NON-ILLUMINATED ACCESSORY BUSINESS SIGNS FOR CAPITAL ONE |
| 31 Oct 2023 | Sign | Signed-off | ERECT NON-ILLUMINATED ACCESSORY BUSINESS SIGNS FOR CAPITAL ONE |
| 20 Jun 2023 | Mechanical Systems | Signed-off | MODIFICATION/ INSTALLATION OF ASSOCIATED DUCTS, PIPING, AND EQUIPTMENT FOR CONFERENCE ROOM 6W8 |
| 3 May 2023 | Plumbing | Permit Issued | PLUMBING WORK AS PER PLANS FILED HEREWITH |
| 31 Mar 2023 | General Construction | Signed-off | RENOVATIONS TO APT 48B AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY |
| 27 Feb 2023 | Mechanical Systems | Signed-off | Filing herewith for HVAC ductwork as per plans filed herewith |
| 4 Jan 2023 | Structural | Permit Issued | INTENT OF DWGS IS TO SHOW THE STR SCOPE OF WORK ONLY FOR A TENANT FITOUT AT 731 LEX AVE AS PER THE PLANS FILED HEREWITH. WORK INCLUDES MINOR REINF OF EX STEEL AND THE ADD OF A FREIGHT ELEV REPLACING AN EX PASS ELEV. NO CHANGE IN USE, EGRESS, OR OCCUPANCY |
| 14 Dec 2022 | Standpipe | Signed-off | Installation of fire hose cabinets on the 2nd floor as indicated on drawings |
| 13 Dec 2022 | Sprinklers | Signed-off | Sprinkler work on the 2nd and 3rd floor as indicated on drawings |
| 1 Dec 2022 | General Construction | Signed-off | Architectural work on the 1st, 2nd, 3rd and 4th floor as indicated on drawings. The EN drawings for lighting are filed under M08022042-I1 |
| 29 Nov 2022 | Structural | Signed-off | Structural work associated with the installation of a convenience stair on the 2nd and 3rd floor as indicated on drawings |
| 29 Nov 2022 | Plumbing | Signed-off | Plumbing work on the 1st and 2nd floor as indicated on drawings |
| 29 Nov 2022 | Mechanical Systems | Signed-off | Mechanical work on the 2nd and 3rd floor as indicated on drawings |
| 19 Sep 2022 | Plumbing | Signed-off | Installation of plumbing piping on the 1st and 2nd floor as indicated on drawings |
| 29 Jun 2022 | Mechanical Systems | Signed-off | Mechanical work on the mezzanine level and 1st floor (Capital One) as indicated on drawings |
| 10 Jun 2022 | Sign | Signed-off | Propose to install non-illuminated non-advertising sign. No change in use, egress, or occupancy |
| 10 Jun 2022 | Sign | Signed-off | Propose to install non-illuminated non-advertising sign. No change in use, egress, or occupancy |
| 21 Apr 2022 | General Construction | Signed-off | Filing herewith for a temp structure as per plans |
| 20 Apr 2022 | General Construction | Signed-off | Storefront renovation on the 1st floor (Capital One |
| 31 Mar 2022 | Mechanical Systems | Signed-off | Modification to mechanical/HVAC on part of 1st floor as indicated on attached plans. There is no change in egress, use or occupancy |
| 28 Feb 2022 | Construction Fence | Signed-off | INSTALLATION OF A TEMPORARY CONSTRUCTION FENCE AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. CONSTRUCTION FENCE TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2014 |
| 18 Feb 2022 | Sprinklers | Signed-off | Sprinkler work on the mezzanine level and 1st floor (Capital One) as indicated on drawings |
| 17 Feb 2022 | Plumbing | Signed-off | Plumbing work on the mezzanine level and 1st floor (Capital One) as indicated on drawings |
| 14 Feb 2022 | General Construction | Signed-off | General construction on the 1st floor and mezzanine (Capital One) as indicated on drawings |
| 14 Feb 2022 | Structural | Signed-off | Structural work on the mezzanine level and 1st floor (Capital One) as indicated on drawings |
| 17 Jan 2022 | Mechanical Systems | Permit Issued | Mechanical work on the SC1 and SC2 level and the 1st and 2nd floor as indicated on drawings |
| 14 Jan 2022 | General Construction | Permit Issued | Architectural work on the SC1 and the SC2 level and the 1st and 2nd floor as indicated on drawings |
| 9 Nov 2021 | Sprinklers | Signed-off | PLUMBING AND SPRINKLER WORK FOR TENANTS FITNESS CENTER RENOVATIONS |
| 2 Nov 2021 | A2 | ISSUED | — |
| 28 Oct 2021 | General Construction | Signed-off | Interior renovations on part of 1st floor (former coffee retail). No change in occupancy, use or egress |
| 18 Oct 2021 | Plumbing | Signed-off | modification to sprinkler and plumbing on part of 1st floor as indicated on attached plans. There is no change in egress, use or occupancy |
| 31 Aug 2021 | Plumbing | Signed-off | PLUMBING DEMOLITION ON THE 1ST FLOOR AS INDICATED ON DRAWINGS |
| 30 Aug 2021 | General Construction | Signed-off | DEMOLITION OF NON LOAD BEARING PARTITIONS ON THE 1ST FLOOR AS INDICATED ON DRAWINGS |
| 30 Aug 2021 | Mechanical Systems | Signed-off | MECHANICAL DEMOLITION ON THE 1ST FLOOR AS INDICATED ON DRAWINGS |
Showing the 50 most recent of 150. The full set is available in the interactive report.
About this page
Compiled from New York City public records — data retrieved 5 days ago. Coverage on this parcel: 14 of 15 record groups populated. The derived figures — unused floor-area ratio, buildable area, the assessed-value trend and the per-unit ratios — are calculated by us and appear in no public dataset; the formulas are in the methodology.
This is a research tool, not advice. It is not a title search, a lien search, a survey or an inspection, and it does not replace any of them. If a figure here matters to a decision, verify it at the source. See Terms.